The parking lot at Harmony School in Châteauguay will be expanded and soccer fields will be added to the school grounds.
Work began on Monday, March 22nd. Excavation M Leclerc, from La Présentation, was awarded the City of Châteauguay contract valued at $378,000 following a call for tenders. Competition was fierce. According to the Quebec government’s electronic system for calls for tender (Système électronique d’appel d’offres – SEAO), 19 companies submitted a quote for completing the work.
On its website, the City of Châteauguay specified that the project will be undertaken in two phases:
- Phase 1, from March 22 to mid-April: creation of a retention basin, installing pipes, building the foundations, etc.
- Phase 2, from June 28th to mid-July: building the concrete borders, laying asphalt, levelling future soccer fields, and hydraulic seeding.
(Translation Amanda Bennett)